Railway turnout number selection usually begins with one question: should the project use a No. 9, No. 12 or No. 18 turnout? A higher number generally describes a flatter crossing angle and a longer, gentler diverging route. It does not, by itself, state the permissible diverging speed. The correct choice also depends on the actual turnout radius, switch geometry, cant and cant deficiency, axle load, vehicle characteristics, available track length and the governing railway rules.
This guide explains the difference between European 1:N crossing ratios and North American frog numbers, compares common No. 9, No. 12 and No. 18 designations, and shows how a Chinese conventional-speed rule set treats minimum turnout numbers. It also covers frog construction, inspection points, track-circuit interfaces and the information a supplier needs to check a railway turnout enquiry.
A turnout number is associated with the crossing geometry, but railway systems do not all use the same notation. Before comparing a frog number or calculating a crossing angle, identify the convention shown on the drawing or specified by the infrastructure manager.
European 1:N crossing ratio: N = 1 / tan(α), where α is the overall crossing angle used by that design convention. A 1:9 ratio means one unit of lateral spread for nine units of longitudinal distance in the idealised geometry.
North American frog-number convention: N = 0.5 × cot(α / 2), or α = 2 × arctan(1 / 2N). The theoretical angles for No. 9, No. 12 and No. 18 are approximately 6°21′35″, 4°46′19″ and 3°10′56″ respectively. Under the European 1:N convention, the corresponding values are approximately 6°20′25″, 4°45′49″ and 3°10′47″. These values are close, but they are not identical; do not mix the conventions in a specification.
In North American field practice, the frog number can also be checked by measuring the change in gauge-line spread along the frog. For example, where the spread increases from three inches to four inches, the longitudinal distance between those measurement locations gives the frog number in inches under the stated method. This is a field convention for suitable frog geometry, not a universal measurement procedure for every curved or special crossing.

The theoretical crossing angle, the physical frog nose and the gauge-line measurement locations are not the same point. On curved frogs, the local angle can change along the crossing. For design, replacement or acceptance, use the approved turnout drawing and the measurement method specified by the relevant railway authority or manufacturer. State whether the enquiry uses European 1:N notation or a North American frog number.
A larger turnout number normally corresponds to a flatter crossing angle. It is usually associated with a larger diverging radius and a longer turnout, but the number alone does not define the complete lead curve or the overall turnout length.
Catalogue screening approximation for a straight frog: N ≈ √(6R / G), or R ≈ G × N² / 6, where R is in feet and G is the track gauge in inches. This approximation is reproduced in the Harmer Steel frog catalogue; it is not a substitute for the turnout manufacturer's geometry or a railway design calculation.
For illustration, using G = 56.5 in (standard gauge), the approximation gives about 763 ft (232.5 m) for No. 9, 1,356 ft (413.3 m) for No. 12 and 3,051 ft (929.9 m) for No. 18. Treat these as catalogue screening figures only. Actual turnout radius depends on the switch lead, closure-rail curve, crossing geometry and the specific design.

A larger number can support a higher diverging speed because the route is generally less sharp, but permissible speed is a design outcome, not a direct conversion from frog number. The designer must also check actual curve radius, cant or superelevation, cant deficiency, transition geometry, switch-rail curvature, crossing design, wheel and vehicle characteristics, locking and detection, maintenance condition and the applicable operating rules.
The footprint grows as the geometry becomes flatter. A longer turnout may need more throat length, more sleepers and fastening components, a longer possession for installation and more track to inspect. The practical comparison is therefore not simply No. 9 versus No. 18: it is the required diverging speed and traffic against the available layout, lifecycle cost and maintenance strategy.
The following is a worked example from the 2014 edition of the Rules of Railway Technology Management for conventional-speed railway. It illustrates how one national rule set links turnout selection to route function, stopping movements, axle load and special layouts. It is not a universal rule for overseas networks, private sidings or every industrial railway; the applicable current rule and project specification must be checked.
1. The through-route speed of a mainline turnout must not be lower than the design speed of the railway section in which it is installed.
2. For a single turnout, the crossing number is selected with reference to the highest speed permitted on the diverging route.
3. A single turnout used to receive or dispatch stopping passenger trains on the diverging route must be no smaller than No. 12.
4. A mainline single turnout used to receive or dispatch stopping freight trains must be no smaller than No. 12 at intermediate stations and No. 9 at other stations.
5. On a line with an axle-load limit exceeding 25 t, a mainline single turnout must be no smaller than No. 12.
6. Other single turnouts within the scope of the cited rules must be no smaller than No. 9.
7. A double-slip turnout in a constrained yard must be no smaller than No. 9. Double-slip turnouts should generally be avoided on mainlines; where one is unavoidable, the minimum is No. 12.
8. On hump-yard tracks, symmetrical turnouts must be no smaller than No. 6, and three-way turnouts must be no smaller than No. 7.
9. On depot tracks, symmetrical turnouts must be no smaller than No. 6.

The exceptions matter. The rule does not say that every turnout in every depot must be No. 9; it gives a separate minimum for symmetrical turnouts on depot tracks. Nor does it create a universal speed table such as “No. 12 equals 120 km/h”. The diverging speed must be checked against the design geometry and the operating rules.
Article 47 of the same conventional-speed rule set also addresses frog type on mainlines. In the cited text, sections with a permitted line speed up to and including 120 km/h use fixed frogs. Above 120 km/h up to and including 160 km/h, or where the specified freight axle load reaches 25 t, the text allows a movable-point frog or a fixed frog with external locking. Above 160 km/h, it requires a movable-point frog with external locking. Confirm the applicable edition, route category and project amendments before using these thresholds.
If a larger number gives a flatter crossing, why not specify the largest available turnout everywhere? Space, cost and operational needs set the limit. A larger design generally occupies more length and may require a longer switch panel, longer closure rails and a different fastening and sleeper arrangement.
The trade-off is project-specific. A compact freight yard may prioritise available throat length and low-speed shunting; a passenger route may require a higher diverging speed and more generous geometry. A high-speed mainline may use specialised turnout designs and dedicated rules that cannot be reduced to a single No. 18 rule of thumb. Compare the design speed, maximum axle load, traffic pattern, layout envelope, maintainability and lifecycle cost before choosing the number.
Do not select a turnout from the number alone or copy a number from a nearby line. Ask for the approved turnout drawing or design data: gauge, crossing ratio convention, lead-curve radius, switch-rail geometry, diverging speed, cant strategy, axle load and vehicle duty. If a supplier is asked to recommend a number, provide those inputs and identify the governing railway standard.

A conventional single turnout is commonly described in three functional panels: the switch panel, the closure-rail panel and the crossing panel. Where the switch panel meets the closure panel, a pivot heel is closed by a bent bar - see the heel joint bar page.The exact component arrangement varies with turnout design, rail section, gauge and railway standard.
The switch panel contains the movable switch rails (also called point blades) and the fixed stock rails. At the heel of the switch, those two rails are held at a fixed interval by spacing blocks - see the turnout spacer block page.Stretcher bars or other switch-connecting arrangements coordinate the blades. Slide chairs or plates support the moving rails; some designs use rollers. Braces, stops, gauge components, fasteners and the operating and locking equipment maintain the required position and clearances.
The closure-rail panel connects the switch panel to the crossing.Plates in that panel are specified against their own drawing; the railway baseplate page covers standards, materials and testing. It commonly includes the lead rails or closure rails, sleepers or bearers, plates, spacers and fasteners. The curve and rail section must match the approved turnout geometry; do not assume the closure rails are interchangeable between two turnouts with the same nominal number.
The crossing panel guides the wheelset through the point where the two rail paths intersect. A fixed crossing typically includes a nose and wing rails, with a check rail (often called a guard rail in some railway conventions) opposite the crossing to control the path of the other wheel. Some designs use a self-guarded or movable-point arrangement. Terminology and detail vary by region, so the drawing should define the component names.
British usage commonly refers to switch rails as points or point blades and to the frog as the crossing; North American documents commonly use frog and guard rail. A purchase specification should state the applicable terminology, drawing number, rail profile, gauge and handedness.Rod names follow the same pattern across standards; see switch rod vs stretcher bar.
For projects requiring a complete assembly or a defined component package, ATK can review the requested supply scope against the approved drawing, rail section, gauge and applicable standard. See the railway turnout assembly page for the product scope; final configuration and manufacturing feasibility must be confirmed for each enquiry.
Frog selection has two separate dimensions. The first is the operating arrangement: fixed-point or movable-point. The second is the construction method and material, such as cast high-manganese steel, an alloy-steel combined construction or a fabricated assembly. These are not three mutually exclusive types on one classification axis. How long that frog then lasts, and what ends its life, is a separate question — see why railway frogs fail.

A fixed-point frog keeps the crossing nose in a fixed position. The wheel passes through the designed flangeway and running-surface transition, so impact, wheel guidance and wear depend on the crossing geometry, wheel profile, traffic and maintenance. Fixed frogs may be cast or fabricated and may use different specified materials.
For Chinese railway projects, TB/T 447-2020 covers high-manganese steel frogs. TB/T 3467-2024 covers alloy-steel combined frogs for conventional-speed railway turnouts and is a separate current standard. A fabricated frog assembled from machined rail sections is another construction approach; its acceptance requirements should be stated in the project specification and drawing.
A movable-point frog changes the position of the crossing nose or point to suit the selected route and reduce the discontinuity associated with a fixed flangeway. It adds moving interfaces, actuation, locking and detection requirements. It should not be described as eliminating every gap or interface in the turnout; the complete design still has clearances and mechanical joints.
Select the frog arrangement from the approved operating speed, axle load, vehicle and wheel profile, crossing geometry, maintenance capability and governing standard. The fixed-versus-movable thresholds in Article 47 are specific to the cited Chinese conventional-speed rules. They do not establish a universal rule that high-manganese fixed frogs are always the default for industrial lines.
Turnout wear does not follow one universal sequence. The areas that need attention first depend on traffic density, axle load, speed, wheel profile, turnout geometry, lubrication, fastening condition, drainage and maintenance practice. A practical inspection focuses on interfaces where movement, impact or wheel guidance occurs.

Inspect the switch-rail tip and the contact with the stock rail for wear, damage, poor fit or evidence that the blade is not closing as designed. Check the slide chairs or plates for contamination, corrosion, wear, roller condition and abnormal operating resistance. The inspection interval and acceptance limits should come from the infrastructure manager's maintenance rules.
Check switch braces, stops, stretcher bars, bolts and locking interfaces for looseness, displacement, cracking or loss of adjustment. Inspect check or guard rails and their fastenings for wear, secure attachment and the required flangeway. At the crossing, examine the nose, wing rails and running surface for batter, cracking, plastic flow or abnormal wheel marks.
Inspect tie plates and baseplates together with sleepers or bearers, gauge, alignment and support. A localised defect can originate in the support or fastening system rather than in the rail component itself. Record the location, dimensions, operating conditions and trend of each defect; use the project maintenance limits to decide whether adjustment, repair or replacement is required.
For turnout support and slide interfaces, see integral cast slide baseplates, which provide product information for the casting and machined seating components. Confirm compatibility with the turnout drawing, rail section, slide arrangement and required inspection basis before ordering.
Turnouts contain rail joints and electrical interfaces, but not every mechanical joint inside a turnout must automatically be insulated. The location and type of an insulated joint are determined by the signalling layout, track-circuit technology, traction-return arrangement and the turnout design.
Where the signalling design requires electrical separation at a joint, the specified assembly must prevent unintended conductive paths through the joint bars, bolts, bushes, washers, end posts, gauge components or supporting steelwork. The number of rails requiring insulation depends on the track-circuit and traction-return arrangement; it should not be generalised as “both rails” for every system. See insulated fishplates for one type of insulated joint assembly.
For applications requiring a bonded assembly, glued insulated rail joints may be specified where the rail section, mechanical duty, electrical requirements and approved installation method are compatible. The joint position relative to a switch, crossing or other boundary must be shown on the signalling and track layout; the product type alone does not determine the placement.
At enquiry stage, state the rail section and hole pattern, track-circuit type, insulated-rail arrangement, required electrical performance, mechanical duty and governing test or acceptance specification. For traction-return systems, confirm how the rail bonds and return-current paths are maintained. Obtain approval from the signalling designer before finalising the joint arrangement.
A useful railway turnout enquiry gives the supplier enough information to check geometry, interfaces and manufacturing scope before preparing a quotation. A turnout number on its own is not enough.

Include the following project data and attach the latest approved layout or turnout drawing:
- Rail section and grade: state the line-rail and turnout-rail profiles if they differ; include the applicable material specification and strength requirements.
- Track gauge and geometry: state the gauge, crossing ratio convention, turnout number, hand (left/right), lead-curve radius, overall length and any connecting-line interface.
- Operating speed: give the through speed and required diverging speed separately. Do not ask the supplier to infer a speed from the turnout number alone.
- Traffic and loading: provide maximum axle load or wheel load, passenger/freight/industrial duty, traffic frequency and vehicle or wheel-profile data where available.
- Crossing arrangement: identify fixed-point or movable-point design and, where known, the frog construction and material standard.
- Switch and actuation: describe the switch rail arrangement, operating equipment, locking and detection requirements, and any interface with signalling.
- Electrical and civil interfaces: identify track-circuit type, insulated-joint locations, traction-return arrangement, sleepers/bearers, support plates, pads and fastening requirements.
- Standards and quality: name the exact standard number and edition, drawings, tolerances, inspection and test methods, acceptance criteria, marking, packing quantity and delivery destination. A customer-named EN, AREMA, DIN or ASTM document should include its relevant part and edition; naming an organisation alone is not a complete specification.
It identifies a crossing ratio or frog number of 12 under the convention used by the railway. Under European 1:12 notation, tan α = 1/12; under the North American frog-number convention, α = 2 arctan(1/24). The resulting angles are close but not identical. State the convention on the drawing or enquiry.
It may be suitable for some low-speed duties, but the number alone is not enough to decide. Check the required diverging speed, axle load, gauge, wheel profile, geometry, available length and the industrial railway owner's rules. The No. 9 minimum in the cited Chinese conventional-speed rules applies only within the relevant rule scope and includes stated exceptions.
Use the measurement method specified by the railway authority or manufacturer. A North American field method measures the change in gauge-line spread and the longitudinal distance between the two measurement locations. It is suitable only for the frog geometry covered by that method; a curved or special crossing may require the drawing or a different reference point.
No. A larger number generally means a flatter crossing angle, but permissible speed also depends on actual radius, cant, cant deficiency, switch geometry, transition, frog design, vehicle dynamics, locking and detection, and the governing operating rules. Use the approved design speed, not a generic number-to-speed chart.
There is no universal answer. Compare the required speed and axle load, wheel profile, crossing geometry, material standard, operating and locking systems, maintenance capability and lifecycle cost. Chinese standards include separate documents for high-manganese steel frogs and alloy-steel combined frogs; the project design determines which applies.
No. The number indicates a crossing geometry convention, not a speed rating. The designer must calculate or verify the actual turnout geometry and check the vehicle, track, signalling and operating constraints under the governing rules.
Send the rail section, track gauge, turnout drawing or number, hand, through and diverging speeds, axle load, vehicle duty, frog arrangement, signalling interface, standard editions, inspection requirements, quantity and destination. A layout drawing is strongly preferred.
State the rail section, gauge, turnout number and notation system, hand, through and diverging speeds, axle load, signalling arrangement and applicable standard editions. Attach the layout drawing, wheel-profile information and any existing site details. ATK can review the requested supply scope and confirm feasibility against the project drawing and agreed technical requirements.